Skip to main content

Blueprint Data Centers Taylor DC

Under ConstructionMonitorReview in progress — 4 sources cited

Proposed size

60 MW

Site area

52 ac

Buildings

3

Building area

135,000 sq ft

Cooling

Air & liquid cooling (closed-loop)

Investment

$1.0B

Developer

Blueprint Data Centers

Blueprint Data Centers is constructing a 60 MW, 135,000-sq-ft colocation campus in three phases on 52 acres at 1601 MLK Jr. Drive in Taylor. The $1 billion project was unanimously approved by Taylor City Council in July 2024, with a 10-year 50% property tax abatement and 50% rebate on construction sales tax. An initial 30 MW is under contract with Oncor. Taylor's proximity to Samsung's $44 billion semiconductor fab drives demand. Closed-loop cooling specified.

Water Impact

Daily water use (estimated range)

540K – 780K gal/day

Water returned per day

None reported

Per Estimated from 60 MW using LBNL benchmark 9,000–13,000 gal/day/MW. Closed-loop cooling confirmed in PUD; actual consumption likely significantly lower., based on Closed-loop cooling confirmed in Taylor City Council approval. Actual consumption may be significantly lower than benchmark estimate.

Estimated daily water use540K – 780K gal/day

vs. 5M gal/day (typical 400 MW facility)

The higher estimate is equivalent to the daily water use of approximately 7,800 households. San Marcos has approximately 25,000 households.

Water intake
540K – 780K gal/day
Lost to evaporation
100%
Returned to system
0% (None reported)
Water flow: 540K – 780K gal/day enters the facility per day. Approximately 100% (780K gal/day) is lost to evaporative cooling and cannot be recovered. No return flow is reported.
For comparison: A sustainable seawater-cooled data center can return over 95% of water to the system. A typical land-based evaporative cooling tower loses 80–95% to evaporation — the primary method used in Texas.

Direct water figures are estimates from permit applications and developer disclosures. Indirect (power generation) figures are calculated estimates. Actual water use depends on technology choices, operating capacity, and weather conditions.

Location

Address: 1601 Martin Luther King Jr. Drive, Taylor, Williamson County, TX

Edwards Aquifer Recharge Zone:Outside recharge zone

Water source: City of Taylor Water

Loading map…

Infrastructure

Water provider
City of Taylor Water
Power provider
ERCOT / Oncor
Under Construction

Permitted — the decision is made, but conditions still matter

The primary decision cannot be undone, but the conditions attached to the approval can still be negotiated or enforced. Officials can be held accountable for permit violations. Community pressure matters for shaping how the project is operated and what monitoring is required.

Timeline

  1. August 1, 2025

    Blueprint Taylor DC under construction — Phase 1 energization targeted for 2026

    Data Center Dynamics reported that Blueprint Data Centers was actively constructing its Taylor campus with Phase 1 energization targeted for 2026 and Phases 2–3 through 2027, as part of the company's accelerated 85 MW Texas capacity expansion.

    Source →(opens in new tab)
  2. July 24, 2024

    Taylor City Council unanimously approves Blueprint Data Centers in 5-0 vote

    Taylor City Council voted 5-0 on July 24, 2024 to approve Blueprint Data Centers' $1 billion campus at 1601 MLK Jr. Drive, including a 10-year 50% property tax abatement and a 50% rebate on construction sales and use tax. Closed-loop cooling was specified in the PUD conditions. The campus is adjacent to the Samsung $44 billion semiconductor fab corridor.

    Source →(opens in new tab)
  3. July 24, 2024

    Taylor Press and TRERC cover $1B Blueprint Data Centers approval

    The Taylor Press and the Texas Real Estate Research Center (TRERC/TAMU) reported on the unanimous Taylor City Council approval of Blueprint's $1 billion data center, noting the project's proximity to the Samsung fab, the 30 MW initial Oncor power contract, and resident concerns about noise, traffic, and compatibility with nearby residential areas.

    Source →(opens in new tab)
  4. January 1, 2024

    Blueprint Data Centers files application with City of Taylor for 60 MW campus

    Blueprint Data Centers submitted its development application to the City of Taylor for a 60 MW, 135,000-sq-ft, three-phase colocation campus on 52 acres at 1601 MLK Jr. Drive. The $1 billion project sought a 10-year 50% property tax abatement and a 50% rebate on construction sales/use tax. All phases were reportedly committed via letters of intent at filing.

    Source →(opens in new tab)

Documents

Sources

  1. 1. Blueprint Projects gets greenlight for data center in Taylor, Texas — Data Center Dynamics, 2024-07-01. Link →(opens in new tab)
  2. 2. Blueprint Projects Data Center — City of Taylor, TX, 2024-07-01. Link →(opens in new tab)
  3. 3. $1B data center project slated for Taylor — Texas Real Estate Research Center, 2024-07-01. Link →(opens in new tab)
  4. 4. Blueprint Taylor DC — datacentermap.com — datacentermap.com, 2026-04-20. Link →(opens in new tab)

Community Notes

Taylor water supply relies on surface water from Lake Georgetown and Brazos River Authority sources, both under drought stress. Closed-loop cooling specified in PUD reduces water consumption. 50% tax abatement reduces near-term revenue. Campus was fully committed via letters of intent at announcement.