Skybox Austin II

Government ReviewMonitorReview in progress — 3 sources cited

Proposed size

30 MW

Building area

148,500 sq ft

Cooling

Closed-loop air-cooled chillers (no evaporative cooling)

Investment

$0.5B

Developer

Skybox Datacenters

Skybox Austin II is a planned 30 MW, 148,500 sq ft data center at 2515 S Kenney Fort Blvd in Pflugerville (Travis County), developed jointly by Skybox Datacenters and Prologis. TDLR building records show a $63 million shell-and-core filing (start Dec 2023, target completion Oct 2024), with an interior fit-out filing of approximately $60 million. Total campus investment is stated at $548 million. The facility uses the same closed-loop air-cooled chiller design as Skybox Austin I.

Water Impact

Daily water use (estimated range)

375 – 54K gal/day

Water returned per day

None reported

Per Skybox closed-loop design (same as Austin I). Developer states less water than 5 households. High estimate from LBNL 9,000 gal/MW/day discounted 80% for closed-loop., based on Skybox has used closed-loop air-cooled chillers exclusively since 2016. Ongoing daily water use negligible.

Estimated daily water use375 – 54K gal/day

vs. 5M gal/day (typical 400 MW facility)

The higher estimate is equivalent to the daily water use of approximately 540 households. San Marcos has approximately 25,000 households.

Water intake
375 – 54K gal/day
Lost to evaporation
100%
Returned to system
0% (None reported)
Water flow: 375 – 54K gal/day enters the facility per day. Approximately 100% (54K gal/day) is lost to evaporative cooling and cannot be recovered. No return flow is reported.
For comparison: A sustainable seawater-cooled data center can return over 95% of water to the system. A typical land-based evaporative cooling tower loses 80–95% to evaporation — the primary method used in Texas.

Direct water figures are estimates from permit applications and developer disclosures. Indirect (power generation) figures are calculated estimates. Actual water use depends on technology choices, operating capacity, and weather conditions.

Location

Address: 2515 S Kenney Fort Blvd, Pflugerville, Travis County, TX

Edwards Aquifer Recharge Zone:Outside recharge zone

Water source: City of Austin Water / Pflugerville

Loading map…

Infrastructure

Water provider
City of Austin Water / Pflugerville
Power provider
ERCOT / Oncor (Austin Energy service area)
Government Review

This is the decision window — showing up now makes the biggest difference

Elected officials weigh in-room presence directly. Twenty people attending a hearing shifts the political calculus more than 200 email signatures. This is also your legal window to create an official record of community opposition, which matters in any subsequent appeal.

Timeline

  1. October 9, 2024

    Interior fit-out construction begins on Skybox Austin 2

    Interior fit-out construction commenced on Skybox Austin Building 2 at 2515 S Kenney Fort Blvd, Pflugerville on October 9, 2024, per TDLR TABS record TABS2024016342. The $86.4 million scope covers 126,150 sq ft of data center interior improvements including hot-aisle containment, electrical busway, cable tray, and a second-story office, with completion targeted June 1, 2025.

    Source →(opens in new tab)
  2. April 16, 2024

    TDLR TABS interior fit-out filing for Skybox Austin 2 (TABS2024016342)

    Austin Data Center 2, LLC filed for the interior fit-out of Skybox Austin Building 2 with TDLR on April 16, 2024 (TABS2024016342). The 126,150 sq ft scope includes hot-aisle containment, electrical busway, cable tray, and second-story office support space, with an estimated cost of $86.4 million, construction start October 9, 2024, and completion targeted June 1, 2025.

    Source →(opens in new tab)
  3. December 1, 2023

    Core-and-shell construction begins on Skybox Austin 2

    Construction on the core-and-shell of Skybox Austin 2 at 2515 S Kenney Fort Blvd, Pflugerville began December 1, 2023, per TDLR TABS record TABS2024003560. The 148,500 sq ft single-story data center shell was designed by Corgan for owner Austin Data Center 2, LLC.

    Source →(opens in new tab)
  4. October 19, 2023

    TDLR TABS shell-and-core filing for Skybox Austin 2 (TABS2024003560)

    Austin Data Center 2, LLC (Skybox) registered the Skybox Austin 2 core-and-shell project with TDLR on October 19, 2023 (TABS2024003560). The 148,500 sq ft, two-story shell at 2515 S Kenney Fort Blvd, Pflugerville carries an estimated cost of $63 million, with construction start listed as December 1, 2023 and completion target October 1, 2024.

    Source →(opens in new tab)

Documents

Sources

  1. 1. Skybox – Austin 2 – TDLR TABS Project Details — Texas Department of Licensing and Regulation, 2024-01-01. Link →(opens in new tab)
  2. 2. Skybox, Prologis moving ahead on massive Pflugerville data centers — The Real Deal Texas, 2024-01-29. Link →(opens in new tab)
  3. 3. Prologis & Skybox file for data centers in Austin, Texas — Data Center Dynamics, 2024-01-29. Link →(opens in new tab)

Community Notes

Same closed-loop cooling design as Austin I; low water risk relative to MW capacity.